Building Project Timeline

In 2016, the district decided to take a two-pronged approach to address facility needs. In addition to the 2017 capital bond referendum, the district adopted a comprehensive long-term facilities maintenance plan, investing more than $10 million annually, to update mechanical systems, maintain our buildings, make site improvements and address other deferred maintenance at our facilities. While some of this work has been done at various sites, Little Canada Elementary is the only site where all mechanical systems have been totally upgraded. 

We are proud that design and construction have been on schedule and on budget throughout the construction period, according to our commitments to the community in the November 2017 bond referendum. Below are the latest updates on project completion, as of August 2021. Photos of renovated or newly constructed spaces are linked in the site descriptions below.

Site Work Scope Construction Start Completion
Aŋpétu Téča Education Center
(formerly Fairview Community Center)
  • New facility
Spring 2020 August 2021
Brimhall December 2018 August 2019
Central Park December 2018 August 2019
Edgerton
  • Capacity additions – classrooms and Friendship Connection updates
  • Flexible learning space and media center
  • Update special education classrooms
December 2018 August 2019
E.D. Williams October 2019 August 2020
Falcon Heights
  • Capacity additions – classrooms and Friendship Connection
  • Renovation of media center and flexible learning spaces
  • Update of special education classrooms and art classroom
October 2019 August 2020
Harambee
  • Addition of district-wide pre-K wing
  • Secure entry and renovation of main office
  • Renovation of media center, flexible learning areas, and Friendship Connection space
October 2019 August 2020
Little Canada
  • Secure entry
  • Capacity additions – classrooms and Friendship Connection updates
  • Flexible learning space and media center
  • Update special education classrooms
August 2018 August 2019
Parkview Center
  • Move office and add new secure entry
  • Capacity additions – additional special education classroom as well as update of existing special education instructional spaces
  • Friendship Connection updates
  • Flexible learning space and media center
  • Renovation of pool and locker rooms
  • Renovate soccer fields
September 2019 August 2020
Roseville Area Middle School September 2019 August 2020
Roseville Area High School (Phase 1) August 2018 December 2019
Roseville Area High school (Phase 2)
  • New auto shop
January 2019 March 2020
Roseville Area High School (Phase 3a)
  • New performing arts center (John J. Thein Performing Arts Center)
Summer 2019 On schedule - December 2021 completion
Roseville Area High School (Phase 3b)
  • Safe and secure entry and office renovations
  • Renovation of career and technical education classrooms (e.g., woodshop, teaching kitchens, textile/fabric lab), music department renovations, special education and learning support updates, conversion of existing science lab spaces
Summer 2019 August 2021