Roseville Area High School

RAHS November 2017 Bond Commitments

  • Adding classrooms to accommodate an additional 300 students
  • Replacing all science labs in new addition/converting existing labs to classroom space
  • Renovating Special Education areas to align with student needs
  • Renovating of all Career & Technical Education areas (including shops, art labs, and FACS labs)
  • Renovating music rooms
  • Renovating media center
  • Creating flexible learning areas for students
  • Adding new secure vestibule including office modifications
  • Adding new auditorium and support spaces for student and community use
  • Renovating existing auditorium for lecture and music performance
  • Expanding cafeteria/new student commons area
  • Upgrading/repairing existing gym areas
  • Converting two practice fields to synthetic turf for student and community use
  • Relocating tennis (new courts, lighting, fencing, etc.)
  • Revising traffic patterns and parking lot to improve pedestrian and vehicular safety

RAHS Project Timeline 

  • June 2021: Start construction of music classrooms
  • Timelines subject to adjustments

Construction Timeline

Area

Planned Completion Date

Science/FACS

November 2019

Auto Shop

Spring 2020

Front Entrance/Main Office

August 2020

Art/Business/IT

Spring 2021

Technology Services

Summer 2021

New Auditorium/Special Ed area/Media Center

Fall 2021

A & B wing commons area/staff offices

Fall 2021